World Cup stadia bid collusion exposed

16 July 2013 - 11:32 By Sapa
subscribe Just R20 for the first month. Support independent journalism by subscribing to our digital news package.
Subscribe now
Mbombela Stadium. File photo
Mbombela Stadium. File photo

Seven major construction and engineering firms met secretly in 2006 to allocate tenders on World Cup stadium projects and to agree on a 17.5% profit margin, according to a report.

The Cape Times reported on Tuesday that the activities of Grinaker LTA, WBHO, Murray & Roberts, Group Five, Concor, Basil Read and Stefanutti were reportedly revealed in settlements and fines the companies agreed to pay the Competition Commission after its probe into collusion in the sector.

According to the Cape Times, the companies reached an agreement in respect of the construction of the 2010 Fifa World Cup stadia, in terms of which they agreed to allocate the Mbombela, Peter Mokaba, Moses Mabhida, Soccer City, Nelson Mandela Bay and Green Point stadia tenders among themselves and to exchange cover prices.

The newspaper reported that several companies including Group Five, Murray & Roberts, Stefanutti Stocks and Aveng, also set up a group called the Western Cape Building Market to share out contracts for three major construction projects in the province.

These were the R4.5 billion stadium in Cape Town, the R87 million Graca Machel Hall at the University of Cape Town and the “flagship” Berg River water project in Franschhoek.

In total, 15 companies had reportedly admitted to rigging 300 projects nationwide, but had been penalised for only 145 projects as the others fell within a period outside the commission’s investigation.

subscribe Just R20 for the first month. Support independent journalism by subscribing to our digital news package.
Subscribe now