Delays in returning generating units at the Kusile (pictured) and Majuba power stations have been blamed for stage 2 load-shedding being implemented on Tuesday. File photo.
Image: Thulani Mbele Delays in returning generating units at the Kusile (pictured) and Majuba power stations have been blamed for stage 2 load-shedding being implemented on Tuesday. File photo.

Power utility Eskom announced on Tuesday that stage 2 load-shedding would be in place from 5pm to 10pm.

This was due to “delays in returning generating units at Kusile and Majuba power stations”, Eskom said in a statement.

Eskom said the “high winter demand brought about by colder temperatures” had also played a role.

It also warned that the chance of rotational power cuts continuing through the week was “high”. 