Load-shedding will be suspended at 10pm on Friday.
In an update Eskom said nine generating units would return to service over the weekend which, combined with expected low weekend electricity demand, would allow the suspension of load-shedding.
However, the power utility cautioned supply will remain severely constrained despite the units, one from Hendrina and two each from Arnot, Duvha, Majuba and Tutuka power stations, returning to service.
“The power system remains severely constrained and volatile. During next week we anticipate to continue relying on the use of emergency reserves to meet demand.”
The ailing utility said 5,353MW was on planned maintenance while another 14,912MW of capacity was unavailable due to breakdowns.
The good news — Eskom to suspend load-shedding in time for the weekend
Image: 123RF/marketlan
Load-shedding will be suspended at 10pm on Friday.
In an update Eskom said nine generating units would return to service over the weekend which, combined with expected low weekend electricity demand, would allow the suspension of load-shedding.
However, the power utility cautioned supply will remain severely constrained despite the units, one from Hendrina and two each from Arnot, Duvha, Majuba and Tutuka power stations, returning to service.
“The power system remains severely constrained and volatile. During next week we anticipate to continue relying on the use of emergency reserves to meet demand.”
The ailing utility said 5,353MW was on planned maintenance while another 14,912MW of capacity was unavailable due to breakdowns.
Eskom has burnt R626m worth of diesel to 'keep the lights on' in April
Eskom CEO Andre de Ruyter said on Thursday the utility did not anticipate load-shedding next week but there were risks making that difficult to guarantee.
“It depends on the weekend and the additional rainfall in Mpumalanga where [our] coal plants are. We may see further impact for Monday next week as the forecast is likely tight,” he said.
On Friday Eskom again apologised for the latest round of load-shedding and said it would continue to closely monitor the power system.
“Load-shedding is implemented only as a last resort to protect the national grid. We therefore request the public to continue using electricity sparingly to reduce the occurrence of load-shedding.
“We will promptly inform the public should there be any significant developments.”
TimesLIVE
Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.
MORE:
Some relief as Eskom announces drop to stage 2 after evening peak
LISTEN | Authorities move into Kliptown’s Chicken Farm to cut illegal power lines as Cele meets Diale family
POLL | How have you prepared for stage 6 load-shedding this winter?
Will the whole of winter be like this? Here are the best and worst case scenarios for load-shedding
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
Most read
Latest Videos