LISTEN | Stage 4 load-shedding extended to Sunday as breakdowns hamper supply

With 15,319MW of capacity unavailable due to breakdowns and 7,210MW on planned maintenance, Eskom has extended stage 4 load-shedding until Sunday morning.

The National Energy Regulator of South Africa has rejected some increases and advised municipalities to stick to its recommended 15.1%. Stock photo.
The National Energy Regulator of South Africa has rejected some increases and advised municipalities to stick to its recommended 15.1%. Stock photo. (123RF/EVGENI BISHTOK )

With 15,319MW of capacity unavailable due to breakdowns and 7,210MW on planned maintenance, Eskom has extended stage 4 load-shedding until Sunday morning.

Thereafter, the electricity utility predicts enforced outages will be at stage 3 until Monday at 5am.

This is due to breakdowns of a generating unit each at Kriel, Majuba and Tutuka power stations over the past 24 hours.

"While some generation units are anticipated to return to service during next week, it is necessary to extend the load-shedding to replenish the emergency generation reserves, which have been depleted by extensive utilisation to limit the amount of load-shedding over the past two weeks," Eskom said.

"The teams are working around the clock to return units to service."

An outlook of load-shedding stages for the week ahead will be provided on Sunday.

TimesLIVE

Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.


Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.

Comment icon

Related Articles