Image: 123RF

Load-shedding will be implemented at stages 2 and 4 during the week as breakdowns hamper Eskom's ability to deliver adequate electricity supplies.

In a statement on Sunday, the utility said: “Stage 4 load-shedding will be implemented from 4pm today until 5am on Monday. Thereafter, stage 2 load-shedding will be implemented from 5am until 4pm. This pattern will be implemented daily until further notice.”

Breakdowns have reduced to 15,798MW of generating capacity while the generating capacity out of service for planned maintenance is 3,099MW.

Over the past 24 hours, a generating unit each at Grootvlei, Kendal, Kriel, Majuba and Medupi power stations was returned to service. But the delay in returning to service a generating unit at Kendal and two generating units at Tutuka is contributing to capacity constraints.

TimesLIVE

Support independent journalism by subscribing to TimesLIVE Premium. Just R80 per month.


subscribe Just R20 for the first month. Support independent journalism by subscribing to our digital news package.
Subscribe now

Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.

Speech Bubbles

Please read our Comment Policy before commenting.