Eskom unfairly shifted the goalposts in multi-billion rand nuclear deal: Court

09 December 2015 - 19:54
By TMG Digital

The losing bidder in a R5 billion tender to replace six steam generators at Eskom’s Koeberg nuclear plant‚ on Wednesday won its challenge in the Supreme Court of Appeal. Westinghouse lost the contract to France’s Areva‚ even though its bid was cheaper.Eskom said awarded the tender to Areva because of "strategic considerations".

This article is reserved for Sunday Times subscribers.

A subscription gives you full digital access to all Sunday Times content.

Please visit SundayTimes.co.za in your desktop to view our latest subscription options.

Already subscribed? Simply sign in below.

Sign In

Questions or problems? Email helpdesk@timeslive.co.za or call 0860 52 52 00.