Stage 6 load-shedding will continue until 5am on Tuesday.
Thereafter, stage 5 will be implemented from 5am until 4pm and stage 6 from 4pm until 5am daily.
“This pattern will be repeated until further notice. Eskom will publish a further update as soon as changes occur,” the power utility said.
Breakdowns were at 17,325MW of generating capacity and planned maintenance at 5,457MW.
Eskom said over the past 24 hours a generation unit each at Camden, Koeberg and Medupi power stations were returned to service. During the same period, two generating units at Kriel were taken offline for repairs.
“The delays in returning a unit to service at Kendal, Kriel, Medupi and Tutuka power stations have contributed to the capacity constraints. However, the team is working to ensure these units are returned to service as soon as possible.”
TimesLIVE
Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.
Load-shedding stage 6 at night and stage 5 in the day until further notice
Image: 123RF/Tebnad
Stage 6 load-shedding will continue until 5am on Tuesday.
Thereafter, stage 5 will be implemented from 5am until 4pm and stage 6 from 4pm until 5am daily.
“This pattern will be repeated until further notice. Eskom will publish a further update as soon as changes occur,” the power utility said.
Breakdowns were at 17,325MW of generating capacity and planned maintenance at 5,457MW.
Eskom said over the past 24 hours a generation unit each at Camden, Koeberg and Medupi power stations were returned to service. During the same period, two generating units at Kriel were taken offline for repairs.
“The delays in returning a unit to service at Kendal, Kriel, Medupi and Tutuka power stations have contributed to the capacity constraints. However, the team is working to ensure these units are returned to service as soon as possible.”
TimesLIVE
Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.
MORE:
Eskom busy fixing fault at Koeberg power station
Eskom: South Africa's winter of discontent
Here to stay: Stage 6 load-shedding will continue until further notice
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
News and promos in your inbox
subscribeMost read
Latest Videos