Stage 6 load-shedding will be implemented from noon on Friday until 5am on Monday.
Eskom said this was "due to a shortage of generating capacity and emergency reserves".
The electricity utility has ramped-up its load-shedding schedules this week, moving from stage 2 on Tuesday to stage 4 in the early hours on Wednesday.
The minister in the presidency responsible for electricity, Kgosientsho Ramokgopa, joined by Eskom’s executives, will address a briefing on Friday afternoon.
In its statement, Eskom said it had lost five generating units over the past 24 hours resulting in a shortage of generation capacity. It also needed to replenish its emergency reserves.
Unplanned outages are currently at 15,901MW of generating capacity, while the capacity out of service for planned maintenance is 5,822MW. "Eskom teams are working tirelessly to ensure that these additional generating units are returned to service as soon as possible."
TimesLIVE
Stage 6 load-shedding kicks in as Eskom darkens weekend
Image: Alaister Russell
Stage 6 load-shedding will be implemented from noon on Friday until 5am on Monday.
Eskom said this was "due to a shortage of generating capacity and emergency reserves".
The electricity utility has ramped-up its load-shedding schedules this week, moving from stage 2 on Tuesday to stage 4 in the early hours on Wednesday.
The minister in the presidency responsible for electricity, Kgosientsho Ramokgopa, joined by Eskom’s executives, will address a briefing on Friday afternoon.
In its statement, Eskom said it had lost five generating units over the past 24 hours resulting in a shortage of generation capacity. It also needed to replenish its emergency reserves.
Unplanned outages are currently at 15,901MW of generating capacity, while the capacity out of service for planned maintenance is 5,822MW. "Eskom teams are working tirelessly to ensure that these additional generating units are returned to service as soon as possible."
TimesLIVE
READ MORE:
Eskom CEO seat has three candidates, will be filled by year-end, says board chair Mteto Nyati
City Power load-shedding chaos: areas hit 3 times between 2pm and midnight
Transnet, Eskom sour season for South Africa's citrus exports
With load-shedding four times higher, Mr Price posts drop in half-year profit
Loss of unit at Medupi a concern that is receiving attention, says Ramokgopa
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
News and promos in your inbox
subscribeMost read
Latest Videos