Eskom announced late on Wednesday that stage 6 load-shedding will continue until further notice.
It said the higher level of blackouts was due to the breakdown of a generation unit at Medupi power station.
“Stage 6 load-shedding will continue until further notice. Eskom will provide an update as soon as any significant changes occur,” said Eskom’s crisis communication manager Menzi Mngomezulu.
On Wednesday afternoon the utility announced the implementation of stage 6 was due to a shortage of generation capacity and would only be implemented from 4pm on Wednesday until 5am on Thursday.
It initially reported breakdowns were at 16,772MW of generating capacity while that for planned maintenance had dropped to 5,807MW.
Eskom said the increase in demand after a long weekend and the reopening of schools had put additional strain on the system.
TimesLIVE
Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.
Stage 6 blackouts to continue until further notice
Image: 123RF/ rclassenlayouts/ File photo.
Eskom announced late on Wednesday that stage 6 load-shedding will continue until further notice.
It said the higher level of blackouts was due to the breakdown of a generation unit at Medupi power station.
“Stage 6 load-shedding will continue until further notice. Eskom will provide an update as soon as any significant changes occur,” said Eskom’s crisis communication manager Menzi Mngomezulu.
On Wednesday afternoon the utility announced the implementation of stage 6 was due to a shortage of generation capacity and would only be implemented from 4pm on Wednesday until 5am on Thursday.
It initially reported breakdowns were at 16,772MW of generating capacity while that for planned maintenance had dropped to 5,807MW.
Eskom said the increase in demand after a long weekend and the reopening of schools had put additional strain on the system.
TimesLIVE
Support independent journalism by subscribing to the Sunday Times. Just R20 for the first month.
READ MORE
Get the candles ready – stage 6 is back
Brace yourself for load-shedding 'worst case scenario' during winter, warns electricity minister
Is Eskom only keeping the lights on for selected religious holidays? — power utility clears the air
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
News and promos in your inbox
subscribeRelated articles
Most read
Latest Videos